Finance News

Project Update | INN



Tungsten West (LON:TUN), the mining company focused on restarting production at the Hemerdon tungsten and tin mine (“Hemerdon” or the “Project”) in Devon, UK, is pleased to provide an update on its Project Financing initiatives and operational activities, against the backdrop of favourable market conditions for the Company’s primary commodities.

Highlights

  • Debt funding progressing well, with a number of potential lenders advanced into term sheet stage
  • Long-lead orders for key equipment and detailed engineering work advanced
  • Onboarding of key Project resources to commence the refurbishment and start-up process
  • Multiple offtake term sheets and letters of intent being progressed
  • Uplift in Project economics calculated using recent tungsten and tin market pricing:
    • The Project’s forecast Net Present Value 7.5% (“NPV”) increases from US$190 million to US$1.7 billion
    • The Project’s Internal Rate of Return (“IRR”) increases from 29% to 197%
    • Near term EBITDA estimates increase over fourfold
  • Publication of updated Corporate Presentation

Jeff Court, CEO of Tungsten West, commented:

“The structural shift in the tungsten market that we have seen since the end of 2024 reflects the ever growing need to provide critical mineral diversification and supply chain resilience to Western economies. The Project Updated Feasibility Study released in August 2025 demonstrated solid financial returns from the Company’s approach to restarting activities at Hemerdon with a greatly improved and robust mineral process flow sheet, plant modifications and access to high quality ore in the pre-existing open pit mine. In the relatively short time since releasing the Updated Feasibility Study, tungsten prices have increased over 200% and tin prices over 70%. As the Company is fully leveraged to market prices, the Project’s economics have vastly improved, underlining the importance of advancing the Project rapidly.

“To this end, in addition to the well-advanced Project Financing, we have accelerated Project re-commissioning work, including ordering long-lead items and engaging key project resources for the refurbishment works. This work programme will have the Company producing tungsten concentrate within 12 months of funding. I look forward to further updating shareholders on our progress across these areas in due course.”

Project Financing update

Debt funding is progressing well, with a number of potential lenders advanced into term sheet stage. These are in addition to the Expression of Interest from the US EXIM bank previously announced on 28 August 2025. Timelines for these work streams are aligned with the Project Financing requirements. The Company will update the market on developments before the end of Q1 2026.

Operational activities

In parallel with ongoing Project Financing, Tungsten West is continuing momentum on workstreams required for project recommissioning. The Company has progressed long-lead orders for key equipment, detailed engineering work, and has begun on-boarding key…



Read More: Project Update | INN

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Accept Read More