Generation Mining Announces Feasibility Study Report Update for the
Generation Mining Limited (TSX: GENM; OTCQB: GENMF) (“Gen Mining” or the “Company”) is pleased to announce positive results on the updated Feasibility Study (“2025 FS” or the “Feasibility Study”) for the Marathon Copper-Palladium Project (the “Project”) located near the Town of Marathon in Northwestern Ontario. All dollar amounts are in Canadian dollars (“$” or “C$”) unless otherwise stated. All references to “Mlbs” are to millions of pounds and “Moz” are to millions of troy ounces and “koz” are to thousands of troy ounces.
Highlights:
- Robust Base Case economics1: An after-tax NPV6% of $1.07 billion, IRR of 28% and 1.9 year payback period based on the 3-yr trailing average metal prices at the effective date2
- Strong critical mineral production during pre-production and the first three years of commercial operation: 151 Mlbs of payable copper, 720 koz of payable palladium and 156 koz of platinum
- Initial Capital: C$992 million3
- Attractive AISC:Life of mine (“LOM”) all-in sustaining costs (“AISC”) of US$2.05/CuEq lb or US$781/PdEq oz3
- At recent long-term consensus prices2: An after-tax NPV6% of $876 million, IRR of 24% and 2.2 year payback period, with 41% of payable metal revenues attributable to copper and 41% attributable to palladium
- At recent spot prices2: An after-tax NPV6% of $749 million, IRR of 21% and 2.4 year payback period, with 44% of payable metal revenues attributable to copper and 37% attributable to palladium.
- Average annual payable metals: 42 Mlbs copper,168 koz palladium, 38 koz platinum, 12 koz gold and 240 koz silver over approximately 13 years of mine life
- Jobs: Creation of over 800 jobs during construction and over 400 direct permanent jobs during operations
- The Next Critical Mineral, Shovel-Ready Project: Fully Permitted for Construction federally and waiting for approval on last permit from the Government of Ontario.
The 2025 FS incorporates the results of the Project optimization work reported by the Company in a news release entitled “Generation Completes Optimization Work for the Marathon Project with Improved Mine Plan and Reduced Capex” issued on November 20, 2024, which focused on two key aspects: 1) optimization of the mine plan to maximize metal production and defer waste stripping in the early years of operations in order to improve early cash flows and reduce the payback period (“Mine Plan Optimization”); and 2) optimization of the process plant design and layout, including sizing of key equipment, plant footprint and foundations, in order to reduce the initial Project capital costs (“Initial Capital Optimization”, and together with the Mine Plan Optimization, the “Optimization Work”).
The Optimization Work has now been further updated to incorporate changes to Mineral Resources, Mineral Reserves, the Life-of-Mine (LOM) mining plan and operating and capital costs, using the same metal price assumptions which formed the basis of the November 20, 2024 news…
Read More: Generation Mining Announces Feasibility Study Report Update for the